The objective of this project is to successfully manufacture, supply, fabricate, install, and commission a 72" GRV (Glass Reinforced Vinyl Ester) seawater piping system for the QAFCO-1 plant. The project aims to provide a durable, corrosion-resistant, and high-performance piping solution to meet the plant's operational requirements. This includes delivering high-quality materials, precision fabrication, and seamless installation, followed by rigorous testing and commissioning to ensure the system’s reliability, efficiency, and compliance with industry standards.
• Concrete breaking and soil manual excavation.
• Installation of well points dewatering system.
• Design, manufacturing, and installation of 2Nos gantries and their railing system.
• Demolishing and disposal of the existing 72” carbon steel seawater header.
• Design, supply, fabrication, and installation of new pipe supports.
• Cutting and re-welding of carbon steel and stainless-steel piping.
• Supply of GRV piping and fittings.
• Installation of GRV piping.
• Lamination of the GRV material.
• Hardness test.
• Service test and commissioning.
• Backfilling.
• Casting of concrete slabs.